Project Highlights

  • 14,000 SF high-end build-out in 100-year-old historical McKinlock Building in Downtown Chicago.
  • Abatement and encapsulation of hazardous materials.
  • Saved the client over $40,000 on MEP value engineering.
  • Tenant occupied space during the construction.
  • Remained on schedule while working through 23 client driven change orders.
  • 14-week long project was compressed and completed in 8 weeks.
Clarion played an instrumental role in managing and completing the buildout of Legalpeople’s leased space on time and, more importantly, on budget. The transformation of the space by Clarion’s entire construction team impressed our tenant, Legalpeople. It was such a pleasure to have trained professionals oversee the buildout of tenant space.  