Type

Tenant Improvement Project

Client

Cushman & Wakerfield

Owner

Adventus US Realty

Property Manager

Cushman & Wakefield

Architect

Ware Malcomb

General Contractor

Clarion Construction, Inc.

Category
Office

Challenges

  • New glass entry way
  • Tired and outdated ceiling needed a cost-effective re-fresh
  • School setting had unique needs

Solution

  • New school entrance was widened to 12 foot wide from existing entry way. Clarion project manager worked with building management to match and adjust the common corridor.
  • Clarion retrofitted t12 fixtures to t8 lighting and replaced the old ceiling tile with new, but left the existing grid and made repairs and touch ups.
  • Clarion carpenters coordinated with furniture vendor to power student desks and teacher podiums.

Services

  • New ceiling tiles
  • Refinished doors and replaced hardware
  • Reconfigured HVAC and added FPB
  • New carpet and paint
  • Retrofit T12 fixtures